Home > Case Studies > Sabre
Case Study: Sabre
Project: Delapidation works prior to tenants resigning of lease.
Value: £205,000
Duration: 12 weeks
Elements: Complete strip and re-roof of 15,000ft.sq building including vertical elevations. Decorations ( internal and external). Flat roof re-felting. Epoxy floor painting. External yard repairs and groundworks. Electrical works and floor coverings.
Building Envelope: 25 year old industrial building. Portal frame with cladding on an industrial estate.
Photographs from this project are shown below...