Case Study: Sabre

Project: Delapidation works prior to tenants resigning of lease.

Value: £205,000

Duration: 12 weeks

Elements: Complete strip and re-roof of 15,000ft.sq building including vertical elevations. Decorations ( internal and external). Flat roof re-felting. Epoxy floor painting. External yard repairs and groundworks. Electrical works and floor coverings.

Building Envelope: 25 year old industrial building. Portal frame with cladding on an industrial estate.

Photographs from this project are shown below...

Safety netting in place & curtain erected to seal off section of building where roof to be stripped & replacedFloor being cleared ready for shot-blast & epoxy floor paintingExternal ground-works to car park surfacesOffice area tidied up for new lettingNew epoxy floor paint & much brighter light levels after new roof lights within replacement roof
*