Home > Case Studies > Icemaster / Yara

Case Study: Icemaster / Yara
Project: Emergency repairs and alteration to existing mezzanine floor structures (installed by others) under a condition of 'imminent collapse' due to overloading.
Value: £29,000
Duration: 2 weeks
Elements: Structural steelwork related to engineers calculations and recommendations to 'recover' a failing structure under continuous and heavy load with vibrating machinery.
Works included specialist equipment lifting at a 'long reach' machinery weighing in excess of 2500kg.
Building Envelope: An industrial portal framed and clad warehouse constructed within the last 15 years.
Photographs from this project are shown below...