Case Study: Berthon Boatyard
Project: To strip & re-clad the external elevations (to 8m high) of a waterside office buiding in parallel with an internal office refurbishment whilst client operations are maintained during a phased installation.
Construction site operated under CDM conditions with Space Ind. Ltd acting as Principal Contractor & Planning Supervisors in Lymington, Hampshire.
Value: £380,000
Duration: 26 weeks
Elements: External insulated profiled cladding / Velux windows / Replacement aluminium double glazing / Internal strip out & demolitions / Internal office partitioning with glass doors / Decoration / Carpeting / Lighting / Power / Data / Central heating / Desking / Seating / Joinery / Display media / Glazing filming.
Building Envelope: A 3,900 sq.ft (360sq.m.) steel portal frame multiple steep angle pitched roofed building with steel & timber external cladding.