Case Study: Visaq

Project: Construction of a Semi Clean Room environment & office fitting out works in Romsey, Hampshire.

Value: 95,000

Duration: 14 weeks in 3 phases

Elements: Powder coated double skin steel partitioning / Suspended Ceilings / Floor Vinyling / Air Conditioning / Ventilation / Racking / Desking / Seating / Decoration

Building Envelope: A standard construction 10,500sq.ft (970sq.m.) industrial building

Photographs from this project are shown below...

Welded seam floor vinyl with steel partitioning & closed ceiling for Clean Room manufacturing area, plus Wardrobe Airconditioning unit positioned prior to integration within Laboratory ceiling & partitions
*