Case Study: Sabre Group
Project: Stripping out of an asbestos roof & re-cladding roof & external vertical elevations with internal refurbishment as part of a dilapidations schedule on behalf of landlord in Wallisdown, Bournemouth.
Value: £100,000
Duration: 5 weeks
Elements: Asbestos Strip Out / Replacement Roofing / Replacement Clad Elevations / Internal Decorations / Cleaning / Power / Lighting / General Building
Building Envelope: A 25yr old 12,630sq.ft (1,173sq.m.) standard construction industrial building.
Photographs from this project are shown below...