Home > Case Studies > Yara

Case Study: Yara

Project: Structural steel plant access platform including relocation of plant and machines.

Value: £30,000

Duration: 2 weeks

Elements: Structural steel decking and stairs, heavy transport of and relocation of plant and machines.

Building Envelope: 20 year old portal frame builds with profiled external cladding elevations.

Photographs from this project are shown below...

Uprated steelwork design to accept heavy machinery on top – 2.5 tonne Dry Ice manufacturing machinesCross bracing, dog leg stairs & steelwork for Plant Platform
*