Case Study: Focal Point Fires

Project: Refurbishment & fitting out of a Warehouse for Assembly & Distribution use in Christchurch, Dorset.

Value: 59,000

Duration: 7 weeks

Elements: Epoxy Floor Painting / Pallet Racking / Partitioning / Fire Shutter Doorway / Fire Alarm / Power distribution

Building Envelope: A 15yr old 17,431sq.ft (1,619sq.m) ground floor + 3,873sq.ft (360sq.m.) First Floor Standard Construction Industrial Warehouse.

Photographs from this project are shown below...

Epoxy floor paint (colour demarcation) with pallet rackingExternal viewEmpty WarehouseEpoxy floor paint (colour demarcation) with pallet racking
*